≈$4.54B Navy DEFINITIVE CONTRACT N0002415C2114

~$4.5B for detail design and construction of carrier CVN 79 — a separate "construction preparation" contract for the same ship ran six years ahead (Huntington Ingalls)

Department of the Navy 2015-06-05 〜 2025-07-31

The U.S. Navy awarded Huntington Ingalls about $4.53 billion for detail design and construction of the aircraft carrier CVN 79. In our collected data a separate "construction preparation" contract for the same ship was awarded in 2009 at about $4.52 billion, bringing the two to about $9.05 billion.

Contract key facts

  • RecipientHuntington Ingalls
  • Contract value$4,540,137,567 (≈$4.54B)
  • BranchNavy
  • Awarding agencyDepartment of Defense
  • Awarding sub-agencyDepartment of the Navy
  • Award typeDEFINITIVE CONTRACT
  • Period of performance2015-06-05 〜 2025-07-31
  • Contract ID (PIID)N0002415C2114

Contract scope (original)

DETAIL DESIGN AND CONSTRUCTION CVN 79

Key points

  • The Navy awarded Huntington Ingalls "detail design and construction, CVN 79," valued at about $4.53 billion ($4,534,837,166 cumulative).
  • A "construction preparation (FY09)" contract for the same ship went to the same company at about $4.52 billion ($4,518,119,480).
  • Preparation was awarded in January 2009 and detail design and construction in June 2015 — preparation running more than six years ahead.
  • Together the two come to about $9.05 billion; a single award value captures roughly half.
  • Both periods end July 31, 2025. Ship name, commissioning, and progress are not in the recorded scope.
  • One carrier carries two contracts — about $4.52 billion for preparation and $4.53 billion for detail design and construction.

1The stage called construction preparation

A ship the size of an aircraft carrier cannot be built in the order of finishing a design and then starting work. The heavy plate that forms the hull, the propulsion plant, and large castings and forgings take years between order and delivery. Beyond that, the dock and machine tools to assemble them, and the recruitment and training of the workforce, all have to move first.

Construction preparation is the stage at which that pre-build work is ordered as a package.

2Preparation running six years ahead

In our collected data the preparation contract was awarded in January 2009 and the detail design and construction contract in June 2015. Money was therefore flowing to the same company more than six years before the substantive build contract. The amounts are comparable too — about $4.52 billion for preparation and about $4.53 billion for detail design and construction, some $9.05 billion together.

Speaking of "the cost of building one carrier" through a single award value captures roughly half of what is actually there.

Construction preparationabout $4.52 billionawarded January 2009
Detail design and constructionabout $4.53 billionawarded June 2015, six years later
Together, for one shipabout $9.05 billionone award alone is half

3What the record shows

Both are DEFINITIVE CONTRACT, and the periods of performance end on the same date, July 31, 2025. The ship's name, its planned commissioning, and construction progress are not in the recorded scope, and this site does not write beyond what is recorded.

Why it matters

Large warship procurement divides by stage, so public data spreads spending on one ship across several rows, and cost per ship requires grouping by hull identifier. For a shipbuilder, the preparation award is what sets the timing of capital investment and hiring, making the pre-contract stage the milestone that matters in business planning.

FAQ

What data is this?
A single Department of Defense (DoD) federal procurement contract recorded in "USAspending," the U.S. open government-spending dataset. The recipient, awarding component, value, and scope are public. This site is not an official U.S. government website.
Is the amount final?
It is a cumulative figure as of collection. Large defense contracts accumulate modifications over many years, so amounts change. The latest figure is available at the source, USAspending.
What does construction preparation involve?
Securing long-lead material such as heavy plate, the propulsion plant, and large castings and forgings, plus preparing the dock and machine tools and recruiting and training the workforce — the work that must precede building.
Is this award the cost of one carrier?
No. Contracts for the same ship divide into preparation, design, and construction, so they have to be grouped by hull identifier (CVN 79). Within our collection the two together come to about $9.05 billion.

Sources (primary)

This article is an independent organization based on the U.S. official spending data below. Verify the exact, latest details with the official source.

#Defense#DoD#Navy#Aircraft carrier#Shipbuilding#Long-lead material#Federal contracts
Disclaimer: This site independently summarizes and classifies information based on official data sources. Always verify the latest and accurate information with the official sources. Content on finance, health, legal, and security is information, not advice. This site is not an official website of the U.S. government.