C-5M upgrade long-lead items: ~$5.0B — the choice to rebuild rather than buy new (Lockheed Martin, Air Force)
The U.S. Air Force awarded Lockheed Martin advance procurement of long-lead items for the low-rate initial production phase of the C-5M Reliability Enhancement and Re-engining Program, valued at about $5.00 billion, running from April 2007 to January 2019. The decision to modernize existing transports rather than build new ones is compressed into the contract title.
Contract key facts
- RecipientLockheed Martin
- Contract value$4,996,841,729 (≈$5B)
- BranchAir Force
- Awarding agencyDepartment of Defense
- Awarding sub-agencyDepartment of the Air Force
- Award typeDEFINITIVE CONTRACT
- Period of performance2007-04-30 〜 2019-01-31
- Contract ID (PIID)FA862507C6471
Contract scope (original)
ADVANCE PROCUREMENT OF LONG LEAD FOR LRIP FOR C-5M RERP
Key points
- The Air Force awarded Lockheed Martin advance procurement of long-lead items for the LRIP phase of the C-5M RERP.
- Value about $5.00 billion ($4,996,841,729 cumulative); period April 30, 2007 to January 31, 2019.
- Advance procurement means securing materials ahead of the main contract; long lead means items with long order-to-delivery times.
- RERP is the Reliability Enhancement and Re-engining Program — re-engining existing C-5 aircraft rather than building new ones.
- Recorded outlays in this data are zero, but older contracts are less completely recorded, so that does not mean no money was spent.
- Advance procurement, long lead and LRIP stack in one title: buying long-lead material for pre-serial production ahead of the main contract.
1Three procurement terms stacked in one title
The title of this contract puts three terms of art in a row. Advance Procurement means securing materials ahead of the main contract. Long Lead means items that take a long time between order and delivery. LRIP means Low Rate Initial Production, the stage of building a small number before full production.
Put together, the contract buys the long-delivery materials needed for the pre-production build, ahead of the contract for the build itself.
2Why materials are bought first
Engines, large structural elements, and specialized electronic components can take a year or more to arrive after they are ordered. If the ordering starts only once the main contract is settled, everything downstream slips by the length of that lead time. So the items certain to be needed are carved out and ordered early. Advance procurement of long-lead items is a way of buying time to keep a schedule.
3What RERP chose
RERP stands for Reliability Enhancement and Re-engining Program — re-engining existing C-5 transports and raising their reliability. Designing and manufacturing a new large transport takes enormous time and money, whereas if the airframe structure still has life, replacing the powerplant and systems keeps capability at lower cost and sooner.
The roughly $5.00 billion is not the price of new aircraft; it is the price of continuing to use aircraft that already exist. Recorded outlays in this data are zero, but public outlay fields are less completely recorded for older contracts, so that does not mean no money was spent.
4Three procurement terms stacked in one title
Three terms peculiar to defence procurement stand in this title. Each is a separate concept, and together they mean buying the long-lead material required for pre-serial low-rate production ahead of the main contract.
- 1Advance ProcurementSecuring material alone ahead of the main contract
- 2Long LeadEngines, large structural members, specialised electronics — items taking years between order and delivery
- 3LRIP (low-rate initial production)Building a small number before serial production, to confirm the design and the process
Waiting until the main contract is settled to start ordering delays everything by the length of the lead time. Carving out the items certain to be needed and ordering them first is a way of buying time to keep a procurement plan on schedule. RERP re-engines the existing C-5 transport to raise reliability, and about $5.00 billion is not the cost of buying new aircraft but of continuing to use those that exist.
Why it matters
Advance procurement of long-lead items separates the date a contract is signed from the date production and delivery actually happen, often by years. The point at which a contractor books the award and the point at which orders flow to component suppliers do not coincide either. Anyone laying annual contract totals side by side has to allow for that lag pulling apparent demand peaks earlier than they occur.
FAQ
What data is this?
Is the amount final?
Why buy materials first?
What is RERP?
Sources (primary)
This article is an independent organization based on the U.S. official spending data below. Verify the exact, latest details with the official source.
- USAspending (award details)
- Contract ID (PIID):FA862507C6471